Key Information:
Version of appliance: | V5 |
---|---|
Date of work starting: | August 3rd, 2020 |
Launch date: | June 2021 |
Link to product pack: |
Details on Change:
Reason for change: | Need good warranty terms from the supplier |
---|---|
Description of change: | Supplier is unwilling to provide 2 years warranty |
Picture of the new design: |
Appliance Update Plan:
...
Customer research/ development plan:
...
28th Sept - 22nd Oct 2020
...
Trial order/ pilot plan:
...
February 2021
...
Rollout plan:
...
April 2021
Introduction Checklist:
...
PHASE:
...
DATE COMPLETED:
...
Design approved by product management team:
...
August 2020
...
Design approved by QA:
...
12th-18th November 2020
...
Certification done/ updated:
...
19th Nov-4th Dec 2020
...
Pricing reviewed with commercial:
...
December 7th, 2020
...
Product pack put together:
...
December 2020
...
Key information handed over to supply chain:
...
December 7th, 2020
...
Trial order produced:
...
Dec 7th, 2020 - Jan 15th, 2021
...
Pilot complete:
...
Marketing announcement sent out:
...
June 3rd, 2021
...
New orders switch to the new design: