Key Information:
Version of appliance: | V5 |
---|---|
Date of work starting: | August 3rd, 2020 |
Launch date: | June 2021 |
Link to product pack: |
Details on Change:
Reason for change: | Need good warranty terms from the supplier |
---|---|
Description of change: | Supplier is unwilling to provide 2 years warranty |
Picture of the new design: |
Appliance Update Plan:
Customer research/ development plan: | 28th Sept - 22nd Oct 2020 |
---|---|
Trial order/ pilot plan: | February 2021 |
Rollout plan: | April 2021 |
Introduction Checklist:
PHASE: | DATE COMPLETED: |
---|---|
Design approved by product management team: | August 2020 |
Design approved by QA: | 12th-18th November 2020 |
Certification done/ updated: | 19th Nov-4th Dec 2020 |
Pricing reviewed with commercial: | December 7th, 2020 |
Product pack put together: | December 2020 |
Key information handed over to supply chain: | December 7th, 2020 |
Trial order produced: | Dec 7th, 2020 - Jan 15th, 2021 |
Pilot complete: | |
Marketing announcement sent out: | June 3rd, 2021 |
New orders switch to the new design: |
Add Comment