Torch V2-Appliance Update
Key Information:
Version of appliance: | V2 |
---|---|
Date of work starting: | August 11th, 2020 |
Launch date: | March 2021 |
Link to product pack: | Â |
Details on Change:
Reason for change: | Change the torch appearance |
---|---|
Description of change: | We want to change the torch so that it can have more edges |
Picture of new design: | Â |
Appliance Update Plan:
Customer research/ development plan: | Feb 9th - March 12th, 2021 |
---|---|
Trial order/ pilot plan: | Dec 7th, 2020 - Feb 8th, 2021 |
Rollout plan: | March 2021 |
Introduction Checklist:
PHASE: | DATE COMPLETED: |
---|---|
Design approved by product management team: | August 11th, 2020 |
Design approved by QA: | 19th - 30th October 2020 |
Certification done/ updated: | Oct 19th - Nov 19th, 2020 |
Pricing reviewed with commercial: | November 2nd, 2020 |
Product pack put together: | Nov 2nd - Dec 5th, 2020 |
Key information handed over to supply chain: | November 2nd, 2020 |
Trial order produced: | Dec 7th, 2020 - Feb 8th, 2021 |
Pilot complete: | Â |
Marketing announcement sent out: | March 15th, 2020 |
New orders switch to new design: | Â |